CPM MECHANICS is Must Reading ...

... For Architects and Engineers

And for three good reasons: Owners are to be found at the center of the Problem, the Impact, and the Solution. And they look to YOU for advice on how to make things better.

Quick Links to Below


Problem: How Owners Cause Project Delays

Not knowing it, various actions and choices that Owners routinely and habitually make qualify Owners as the #1 cause of their projects slipping their schedules!

How is this possible? Because they rely on the advice of consultants and experts who, in large part, are also unaware that the Project Management practices advocated for "most projects most of the time," are not especially well suited for the Construction Industry. As a result, by following "recommended practices" to a large extent Owners are only making things worse -- going along, "fat, dumb, and happy" as the expression goes.

And adding insult to injury, a number of "standard practices" within the Construction Industry have only further weakened the General Contractor's ability (or willingness) to responsibly manage the project, and guide it to a successful and timely completion. When does this happen? How about ... during design, during procurement, in the contract, in Owner attitudes and posture, in Owner expectations and demands, in an overall missing sense of fairness all around. All of this is discussed on the other pages of this website. (Top of Page)


Impact: Owners Bear the Maximum Cost

While all parties to the project suffer when schedules slip, it is the Owner that bears the maximum cost.


Solution: Only Owners Can Improve conditions

If the previous comments are discouraging, then find solace in knowing that the Owner is in the best position to make things better. Specifically, the Owner has the power, authority, influence to change the way projects are managed.

As the Owner's key agent, you are in the best position to influence the kind of change required to change the outcome of projects on which you serve as a Design Professional. The Owner looks to you for sound advice on Best Practices, and for what they should expect from the other key players on project: the design and construction professionals.

Knowledge is Power

You have to ask yourself, how did things get so bad? With the proliferation of Project Management standards, training, certifications, conferences, literature and discussions .... why are projects not doing better? Why do they actually seem to be getting worse?

Follow the money! Ask yourself, who knew? To be sure, several cottage industries have grown up around the failure of projects: lawyers and claims consultants to name just two. But there are also those who profit from promoting the Conventional Wisdom: trainers, management consultants, certifying agencies, and so forth. Do these entities know that the generic Project Management model is not especially well suited for Construction? Most don't. And those who do know, keep that fact to themselves.

Design Professional are not your run-of-the-mill "projecy management consultants" mentioned in the previous paragraph. You are a special breed of experts: who a well-developed understanding of the Owner's unique bundle of needs, wants, desires, and expectations. That is what qualifies you to function as a value-adding Design Professional.

But this powerful position of influence does not relieve you of continuing education, of learning how to do things better than they have been done.

You can't fix what you don't know To Be broken.

All solutions begin with understanding. Here is just a sampling of what ICS-Research would like Design Professional to know about the cause of Schedule Slippage:


We Need a Different, Better Approach

Albert Einstein's famous comment about insanity comes to mind: doing the same thing over and over and expecting a different outcome.

ICS-Compendium Offers Two Competing Solutions

The ICS-Compendium includes two separate Solutions to the Problem of ineffective Project Time Management.

The Project Schedule is Central to Both Solutions

Both Project Management models are predicated on the establishment and maintenance of a comprehensive, credible, and vibrant Project Execution Strategy (Project Schedule). This book, CPM Mechanics, is the first of two books that WILL fully explain how to most effectively design, development, and maintain reliable Project Schedules.

The problem is that much of what we have been taught about the creation and maintenance of schedules is significantly dysfunctional. Keeping in mind Einstein's admonition, we would be wise to take a sober look at our current approach to Planning and Scheduling, with a critical eye toward what works, and what does not.

For instance, ICS-Research has discovered that the current scheduling practices are inherently flawed in four key areas:


ICS-Compendium was Written for Owners

There is so much that is wrong with how we manage our construction projects that the solutions cannot be fully discussed in a single volume. That is why the ICS-Compendium has multiple volumes. Each book speaks to a different aspect of the Problem and Solution.

For each Project Management Model (Dominant or Cognitive) there are four volumes, each speaking to a different aspect of the model:


How Well are You Managing the Design Effort?

We may have left the best for nearly the last but .. just how well are you, as a Design Professional, managing your own work? The design community has a pretty unimpressive track record when it comes to completing the design phase on time. Of course Design Professionals are quick to point the finger at an indecisive and vascillating Owner.

And that is surely part of the reason why procurement windows continually slip. But it is not the entire explanation, is it? There is still the painful truth that Design Professionals are notoriously bad at managing their time.

Well, by learning about how the Critical Path Method really works, not only will you be able to better advice your Owner-clients, you will also be able to improve your in-house ability to plan, schedule, and perform your work in a timely manner.

And the next time the Owner drags you into a time-consuming detour into some esoteric exploration of this or that, you will be able to quantify the impact on downstream deadlines.


CPM Mechanics is Essential Reading!

Not only is CPM Mechanics the first book in the Dominant Project Management Series, it is also the first book in the entire ICS-Compendium ... which means that the Cogntiive Project Management Series is predicated on it as well.

Project Schedule is at the Epicenter of Project Management

That should make perfect sense to you since, at the end of the day, the Project Schedule stands at the very epicenter of Project Management. Think about it:

The main message about project management, for architects, is that there is much more to Project Time Management than mere creation and maintenance of a construction work schedule (also known as construction planning and management).

Start Your Learning Journey with CPM Mechanics

So it all comes down to this: do you want to improve the outcome of projects on which you serve as a Design Professional? If you do, then you must help your Owners to better understand how they are in the best position to make that happen. You must guide them as they change their expectations, contracts, attitudes, and actions to afford a better tomorrow.

But you cannot bring about improvements by doing the same things that have proven ineffective to date. You need to learn what is good in the current Project Management model, and what could stand changing.

Begin by educating yourself. Wipe away the confusion about the technical stuff that has alluded you all along. In so doing, expose the flaws in the current model. Learn what works ... and what does not.

CPM Mechanics is required reading ... if you really want to change your Project Management track record. (Top of Page)


 

ICS CompendiumDominantPMSeriesVolume 1Volume 1Volume 3Volume 4SpacerCognitive PM SeriesVolume 5Volume 6Volume 7 Volume 8Spacer ReferenceVolumes Volume 9 volume10 Spacer TIME ConceptTechnologyIdeologyMethodologyEcologySpacerFACEConceptProject FacilitationProject AdministrationProject CoordinationProject Execution
The International Center for Scheduling, Inc. | PO Box 80915, Rochester Michigan, 48308 | Phone: (877) 427-5665 | Fax: (248) 415-5548
Copyright 2012 International Center for Scheduling, Inc. | All rights reserved.